In
July 1995, the Government of Tanzania began construction of the
180–megawatt Lower Kihansi Hydropower Project (LKHP) in order to meet the
growing electricity demands of its mining and tourism industries. The
World Bank jointly funded the $275 million project along with the European
Investment Bank and development agencies from Norway (NORAD), Sweden (SIDA),
and Germany (KfW). Formally commissioned in July 2000, the project has
been supplying electricity to the Tanzania Electricity Supply Company (TANESCO),
the parastatal that owns and operates the project, since December 1999.
With
its 25–meter dam and relatively small 26–hectare reservoir, the LKHP
appears on paper to be a relatively environmentally benign project. In
spite of its small size, though, the project has had drastic impacts on
biodiversity. The Kihansi Gorge ecosystem is one of only 25 Global
Biodiversity Hotspot as designated by IUCN. It is home to numerous endemic
flora and fauna species that lived in the spray of the gorge’s
800–meter–high waterfall. This waterfall was destroyed by the dam, which
collects water above the gorge, diverts it into a series of tunnels
running into and out of the power plant, and returns the water to the
river at the bottom of the gorge, 6 km downstream. The loss of the spray
from the waterfall, which was laden with mineral–rich silt, has sent the
critically endangered Kihansi Spray Toad and at least two endangered plant
species to the brink of extinction. The previously unknown Kihansi Spray
Toad exists nowhere else on earth, and the dam has already destroyed over
90% of its habitat. Efforts to rescue the toad through a captive breeding
program and the installation of a sprinkler system in the gorge have
failed to stabilize population levels.
The
pending extinctions are a direct result of the World Bank’s failure to
require a thorough Environmental Impact Assessment before it financed the
LKHP. It also failed to require that the project’s design and operation be
changed after environmental impacts were better understood. This is a
clear violation of the Bank’s own policies, and a flagrant breach of their
commitments under the International Convention on Biological Diversity.
Alternatives
exist that would sustain the Gorge Habitat and ensure that the LKHP
remains economically viable. These alternative proposals would increase
instream bypass flows to seven cubic meters per second in order to create
sufficient spray from the waterfall. Nevertheless, the World Bank and
other funders have opted not to oblige the Government of Tanzania to
implement this option.
The
following briefly evaluates the project against the guidelines of the
World Commission on Dams.
Sustaining
Rivers and Livelihoods
WCD
Recommendation
The WCD calls for policies to "maintain selected rivers with high
ecosystem functions and values in their natural state." It further
recommends that consideration of options places priority on "avoiding
or minimizing negative impacts on endangered species" and
"respecting the provisions and guidance of relevant international
treaties."
Reality
on the Ground
Kihansi Gorge is home to an enormous variety of plants and animals. Some
of them, like the Kihansi spray toad and a species of wild coffee, live
only in the waterfall spray zone and are therefore left critically
endangered by this project. The growing likelihood that the LKHP will lead
to the extinction of these species puts the project in violation with
commitments made by Tanzania and the donor countries under the
International Convention on Biological Diversity.
Impact
Assessment
WCD
Recommendation
The WCD states that all projects "should include an Environmental
Impact Assessment (EIA)" that "complies with international
standards" and is "sufficiently detailed to provide a
pre–project baseline against which post–project monitoring results can be
compared."
Reality
on the Ground
No EIA was carried out before the project began. The World Bank conducted
an environmental assessment as part of the project feasibility study in
the early 1990s. When NORAD joined the project in 1994, it found the World
Bank’s environmental assessment so deficient that it financed an EIA in
1995. This EIA was also found to be of very poor quality because it
contained inadequate data and failed to include adequate water–discharge
and dam management plans. The Kihansi spray toad and two rare plants were
discovered in 1996, one year after dam construction began. For unknown
reasons, TANESCO was not informed of this development until 1998.
Project
Preparation
WCD
Recommendation
The WCD states that
dam developers must provide "sufficient evidence to demonstrate that
proposed mitigation and development measures will be effective in meeting
their objectives."
Reality
on the Ground
Measures put in
place to avert the extinction of the Kihansi spray toad have failed thus
far. Many of the toads involved in the captive breeding program have died,
and the sprinkler system installed in the gorge to simulate waterfall
spray is constrained by problems with silt clogging the tiny sprinkler
openings.
Environmental
Flow Assessments
WCD
Recommendation
The WCD calls for
the definition of "an environmental flow requirement to maintain
downstream species, ecosystems and livelihoods" before the dam is
constructed. It also states, " Releasing tailor–made environmental
flows can help maintain downstream ecosystems and the communities that
depend on them."
Reality
on the Ground
No such
environmental flow requirement was determined prior to construction. Since
then project authorities have resisted efforts to increase downstream
flows, because they claim additional releases will not allow them to
produce enough power. The project feasibility study only analyzed impacts
on habitat flooded by the reservoir. The report failed to mention any
impacts on the Kihansi Gorge ecosystem.
Addressing
Existing Dams
WCD
Recommendation
The WCD states that
problems from existing dams should be addressed: "Management and
operation practices must adapt continuously to changing circumstances over
the project’s life and must address outstanding social issues – The
effectiveness of existing environmental mitigation measures is assessed
and unanticipated impacts are identified; opportunities for mitigation,
restoration and enhancement are recognised, identified and acted on."
Reality
on the Ground
The owners of the
dam have consistently worked to maximize power output and minimize
mitigation efforts. In spite of extensive research concerning the
project’s impact on endangered and threatened species existing within the
Gorge, project authorities and donors refuse to implement necessary
mitigation measures. In fact, TANESCO is operating the dam without rights
to the Kihansi River’s water, so it does not even have permission to
divert any water from the Gorge. The Government of Tanzania is not forcing
TANESCO to comply with existing water rights because of demands for power.